Solar & Battery Regulation & Incentive Programs

Net Metering

Program Overview


Category:
Regulatory Policy
Program Type:
Net Metering
Implementing Sector:
State
State:
Rhode Island
Eligible Storage Technologies:
Geothermal Electric, Solar Thermal Electric, Solar Photovoltaics, Wind (All), Biomass, Hydroelectric, Ocean Thermal, Hydroelectric (Small), Anaerobic Digestion, Fuel Cells using Renewable Fuels
Website:
http://www.energy.ri.gov/renewable/netmetering/
Applicable Utilities:
Investor-owned utilities
System Capacity Limit:
10 MW (effective September 2016)
Systems must be sized to produce no more than an average of three years of annual consumption of energy at the account.
Aggregate Capacity Limit:
3% of peak load for Block Island Power Company and Pascoag Utility District
Other Utilities (National Grid): No aggregate cap.
Net Excess Generation:
Credited at avoided cost; rolled over to next bill or purchased by utility
Ownership of Renewable Energy Credits:
Not addressed
Meter Aggregation:
Allowed
Administrator:
Office of Energy Resources
Applicable Sectors:
Commercial, Industrial, Local Government, Nonprofit, Residential, Schools, State Government, Federal Government, Agricultural, Low Income Residential, Institutional
Utility:
The Narragansett Electric Co
Last Updated:
11/16/2018

Summary

NOTE: In January 2018, National Grid filed approval of its revised net metering tariff to include the changed adopted by RI legislation to expand community solar (remote net metering) to include educational institutions, hospitals, and non-profit corporations. It also removes the 30 MW cap on maximum aggregage amount of remote net metering for public entity facilities, multi-municipal collaboratives, educational institutions, federal government, hospitals or nonprofits.  

Rhode Island allows net metering for systems up to ten megawatts (MW) in capacity that are designed to generate up to 100% of the electricity that a home or other facility uses. The net metered systems size must be sized to produce no more than an average of previous or forecasted three years of annual consumption of the energy at the account. Systems that generate electricity using solar energy, wind energy, ocean-thermal energy, geothermal energy, small hydropower, biogas from anaerobic digestion, or fuel cells using any of these energy sources are eligible. All customers of electric distribution companies including public entities of the state are eligible. The aggregate amount of net-metered systems in Block Island Power Company and Pascoag Utility District is capped at 3% of the peak load for each utility district. In 2014, the aggregate cap for net metering for National Grid was eliminated. Net metered systems may be owned by the customer or be financed by a third party through a lease or power/credit purchase agreements. A third party engaged in financing net metered system is not considered a public utility.  

Net Excess Generation:

The rate credited for kilowatt-hours (kWh) generated that do not exceed the customer's kWh consumption for that billing period is equal to the utility's retail rate (minus a very small conservation charge per kWh). Any excess kWh generation that exceeds 100% but limited up to 125% of the net-metering customers usage during the billing period will be paid excess renewable net-metering credits which is equal to the utilities avoided cost rate, which is calculated as electric distribution company's standard offer service KWh charge for the rate class and Time of Use billing period, if applicable. The excess credit may be carried forward to the next bill or purchased by the utility (at its discretion). To facilitate the administration of billing, utilities may estimate a net-metered customer's generation and consumption over a 12-month period. Otherwise, the rates (including customer charges and demand charges) that apply to a net-metered customer must be the same rates that would apply if the same customer were not net metering. Utilities may not impose any other charges on the net-metered customers. Net-metered customers are exempt from backup or standby rates commensurate with the size of the net-metered system. Utilities may recover through rates any revenue shortfall caused by this exemption.

Meter Aggregation:

A system generally must be owned by the customer of record and sited on the customer's premises (in the same geographic location). However, facilities (1) owned by public entity* or multi-municipal collaborative or (2) owned and operated by a developer on behalf of the public entity or multi-municipal collaborative through “public entity net metering financing arrangement”** are eligible for meter aggregation.  Remote public entity and multi municipality collaborative that apply for remote net metering after December 31, 2018 will cease to receive distribution kWh credit beginning January 1, 2050. Meter aggregation is generally allowed, and special provisions exist to accommodate meter aggregation for farm-based systems that serve facilities in close proximity to each other.

Community Remote Net Metering:

H.B. 8354 enacted on June 2016 authorizes community net metering in the state. The community remote net metering system is defined as a facility using eligible net metered resource that allocates net metering credits to minimum of one account for low or moderate housing recipients accounts, or at least three eligible credit recipient customer accounts, providing that no more than 50% of the credits from the system are allocated to any single recipient, and at least 50% of credits are allocated to other recipients in an amount not to exceed which is produced by annually by a 25 kW system. For instance, if a community net metering system of 250kW assigns to 125 KW to one account, then the remaining 125 kW capacity should be distributed to remaining accounts at more than 25 kW. 

The community net metered systems can be owned by one of the participating customers, or be financed by a third party through lease arrangements or power/credit purchase agreements. The total amount of community net metering is capped at 30 MW until the end of 2018, after which the PUC may decide to expand or modify the aggregate amount after administrative process. On December 2016, the PUC determined that the public housing authorities are considered public entities and are not subject to the 30 MW cap in the community net metering program. Municipal Collaborative facilities, educational institutions, federal government, hospitals, and non-profits are also exempt from this cap. 

 

Rate Design and Cost Allocation study

S.B.0081 enacted on June 2015 requires the Public Utilities Commission (PUC) to consider rate design and distribution cost allocation among rate classes taking into account the effects of net metering and increasing distributed energy resources. The PUC in effect, established a Docket 4545 and required the electric utilities are required to file revenue-neutral allocated cost of service study of all rate classes and propose new rates for all customers in each rate class. On January 2016, the PUC approved National Grid’s request to withdraw their proposed rate change filing determining that no rate revision was required at this time. The PUC however, determined that it was important to continue to review the issues raised in the proceeding, including rate design, net metering, and effects of distributed generation on the grid. The proceeding can be accessed at Docket 4600.  

*A  "public entity" is defined as the municipalities, wastewater treatment facilities, public transit agencies or any water distributing plant or system.

**A "public entity net metering financing arrangement" is defined as an arrangement between a public entity or multi-municipal collaborative and a private entity to facilitate the financing and operation of a net-metered system. Such systems are owned and operated by the private entity and must be located on property owned or controlled by the public entity or one of the municipalities.


Authorities

NameEnacted DateEffective DateExpired Date
R.I. Gen. Laws § 39-26.406/29/201107/29/2011
H.B. 772706/30/201406/30/201406/30/2019
S.B. 0081 (Rate design and cost-allocation)06/16/201506/16/2015
H.B. 835406/27/201606/27/2016
Docket 474312/20/2017